Action Date | Action Description |
---|---|
Jun 30, 2005 | Assent Application Received |
Jul 01, 2005 | Administrative Review for Completeness |
Jul 22, 2005 | Deficient Application - Owner Notification Sent |
Aug 03, 2005 | Deficiency Response Received |
Aug 03, 2005 | Team Review for Completeness |
Aug 03, 2005 | Application Accepted |
Aug 10, 2005 | Biologist Report |
Aug 10, 2005 | Engineering Report |
Aug 11, 2005 | Typist for Processing |
Aug 11, 2005 | Executive Sign Off |
Aug 11, 2005 | Sent to Photo Copy |
Aug 12, 2005 | Permit Approved |
Aug 26, 2005 | HPHC Review Pending |