Action Date | Action Description |
---|---|
Jul 20, 2005 | Assent Application Received |
Jul 22, 2005 | Administrative Review for Completeness |
Jul 29, 2005 | Team Review for Completeness |
Jul 29, 2005 | Application Accepted |
Aug 12, 2005 | HPHC Review Pending |
Aug 12, 2005 | Historical Preservation Approval Granted |
Sep 30, 2005 | Biologist Report |
Oct 03, 2005 | Typist for Processing |
Oct 03, 2005 | Executive Sign Off |
Oct 03, 2005 | Sent to Photo Copy |
Oct 03, 2005 | Permit Approved |
Sep 30, 2008 | Extension of Permit Request |
Oct 06, 2008 | Enforcement Compliance Inspection Required |
Oct 16, 2008 | Extension Approved |
Nov 24, 2008 | Modification Request |
Dec 01, 2008 | Administrative Review for Completeness |
Dec 24, 2008 | Team Review for Completeness |
Dec 24, 2008 | Typist for Processing |
Dec 24, 2008 | Biologist Report |
Dec 24, 2008 | Executive Sign Off |
Dec 24, 2008 | Sent to Photo Copy |
Dec 24, 2008 | Modification Approved |
Jan 23, 2009 | Land Evidence Date |
Sep 09, 2009 | Extension of Permit Request |
Oct 01, 2009 | Enforcement Compliance Inspection Required |
Oct 07, 2009 | Process Extension |
Oct 07, 2009 | Typist for Processing |
Oct 07, 2009 | Executive Sign Off |
Oct 07, 2009 | Sent to Photo Copy |
Oct 07, 2009 | Extension Approved |