Action Date | Action Description |
---|---|
Jul 22, 2005 | Assent Application Received |
Jul 26, 2005 | Administrative Review for Completeness |
Aug 02, 2005 | Deficient Application - Owner Notification Sent |
Aug 12, 2005 | Deficient Application Picked Up |
Oct 05, 2005 | Deficiency Response Received |
Oct 13, 2005 | Deficient Application - Owner Notification Sent |
Nov 09, 2005 | Deficiency Response Received |
Nov 15, 2005 | Team Review for Completeness |
Nov 15, 2005 | Application Accepted |
Dec 01, 2005 | HPHC Historical Preservation No Effect |
Dec 09, 2005 | Typist for Processing |
Dec 09, 2005 | Executive Sign Off |
Dec 09, 2005 | Sent to Photo Copy |
Dec 09, 2005 | Permit Approved |
Dec 09, 2005 | Biologist Report |
Dec 09, 2005 | Engineering Report |
Dec 19, 2005 | Land Evidence Date |