Action Date | Action Description |
---|---|
Jul 26, 2005 | Assent Application Received |
Jul 27, 2005 | Administrative Review for Completeness |
Sep 07, 2005 | Team Review for Completeness |
Sep 07, 2005 | Application Accepted |
Sep 07, 2005 | Category A* (Docks) |
Sep 15, 2005 | HPHC Review Pending |
Nov 09, 2005 | 30 day Public Notice Issued |
Dec 09, 2005 | Public Notice End Date |
Dec 12, 2005 | Plans Received |
Jan 11, 2006 | US Army Corp of Engineers Permit Date |
Jan 12, 2006 | US Army Corps of Engineers Approval Received |
Feb 24, 2006 | Dock sub-committee Approved |
Mar 22, 2006 | Biologist Report |
Apr 10, 2006 | Engineering Report |
Jul 06, 2006 | Typist for Processing |
Jul 06, 2006 | Executive Sign Off |
Jul 06, 2006 | Sent to Photo Copy |
Jul 06, 2006 | Permit Approved |
Jul 14, 2006 | Land Evidence Date |