Action Date | Action Description |
---|---|
Aug 18, 2005 | Assent Application Received |
Aug 19, 2005 | Administrative Review for Completeness |
Aug 26, 2005 | Team Review for Completeness |
Aug 26, 2005 | Application Accepted |
Aug 26, 2005 | Category B assigned |
Dec 02, 2005 | Plans Received |
Dec 09, 2005 | Additional Information Received |
Dec 13, 2005 | 30 day Public Notice Issued |
Jan 13, 2006 | Public Notice End Date |
Jan 18, 2006 | Additional Information Requested from Applicant |
Feb 10, 2006 | Plans Received |
Mar 07, 2006 | Water Quality Certification |
Mar 20, 2006 | Additional Information Received |
Apr 12, 2006 | Engineering Report |
Apr 19, 2006 | Biologist Report |
Apr 19, 2006 | Mail Agenda Notice |
Apr 25, 2006 | Semi-Monthly Meeting Date Scheduled |
Apr 28, 2006 | Mail Agenda Notice |
May 09, 2006 | Semi-Monthly Meeting Held |
May 09, 2006 | Council Approval Granted |
May 09, 2006 | Semi-Monthly Meeting Date Scheduled |
May 19, 2006 | Legal Response/Decision |
May 30, 2006 | Typist for Processing |
May 30, 2006 | Executive Sign Off |
May 30, 2006 | Sent to Photo Copy |
May 30, 2006 | Permit Approved |
May 30, 2006 | Under Review/Decision |
May 30, 2006 | Stipulation Package from Biologist |
May 30, 2006 | Stipulation Package by Engineer |
May 30, 2006 | Supervisor Biologist SignOff |
May 30, 2006 | Supervisor Engineer SignOff |
May 30, 2006 | Ready to Schedule Semi-Monthly Meeting |
Jun 15, 2006 | Correspondence Received |
Jun 19, 2006 | Land Evidence Date |
Aug 11, 2006 | Commencement of Work Notice received |