Action Date | Action Description |
---|---|
Aug 22, 2005 | Assent Application Received |
Aug 23, 2005 | Administrative Review for Completeness |
Aug 24, 2005 | Team Review for Completeness |
Aug 24, 2005 | Application Accepted |
Aug 24, 2005 | Category A* (Docks) |
Aug 30, 2005 | 30 day Public Notice Issued |
Sep 01, 2005 | Engineering Report |
Sep 06, 2005 | HPHC Review Pending |
Sep 15, 2005 | Dock Subcommittee Meeting Held |
Sep 15, 2005 | Dock sub-committee Approved |
Sep 26, 2005 | US Army Corp of Engineers Permit Date |
Sep 29, 2005 | US Army Corps of Engineers Approval Received |
Sep 30, 2005 | Public Notice End Date |
Oct 04, 2005 | Biologist Report |
Oct 04, 2005 | Engineering Report |
Oct 05, 2005 | Typist for Processing |
Oct 05, 2005 | Executive Sign Off |
Oct 05, 2005 | Sent to Photo Copy |
Oct 05, 2005 | Permit Approved |
Nov 29, 2005 | Land Evidence Date |