Action Date | Action Description |
---|---|
Sep 09, 2005 | Assent Application Received |
Sep 12, 2005 | Administrative Review for Completeness |
Sep 15, 2005 | Team Review for Completeness |
Sep 15, 2005 | Application Accepted |
Sep 22, 2005 | Engineering Report |
Sep 26, 2005 | Typist for Processing |
Sep 26, 2005 | Executive Sign Off |
Sep 26, 2005 | Sent to Photo Copy |
Sep 26, 2005 | Permit Approved |
Sep 30, 2005 | HPHC Review Pending |
Oct 17, 2005 | Land Evidence Date |