Action Date | Action Description |
---|---|
Sep 23, 2005 | Assent Application Received |
Sep 23, 2005 | Administrative Review for Completeness |
Sep 26, 2005 | Team Review for Completeness |
Sep 26, 2005 | Application Accepted |
Sep 26, 2005 | Category A* (Docks) |
Oct 05, 2005 | Historical Preservation Approval Granted |
Oct 05, 2005 | HPHC Review Pending |
Dec 01, 2005 | Plans Received |
Dec 09, 2005 | 30 day Public Notice Issued |
Jan 09, 2006 | Public Notice End Date |
Jan 18, 2006 | US Army Corp of Engineers Permit Date |
Jan 20, 2006 | US Army Corps of Engineers Approval Received |
Jan 24, 2006 | Biologist Report |
Jan 24, 2006 | Engineering Report |
Jan 30, 2006 | Plans Received |
Feb 16, 2006 | Supervisor Biologist SignOff |
Feb 16, 2006 | Supervisor Engineer SignOff |
Feb 17, 2006 | Executive Sign Off |
Mar 30, 2006 | Ready to Schedule Semi-Monthly Meeting |
Mar 30, 2006 | Mail Agenda Notice |
Apr 11, 2006 | Semi-Monthly Meeting Held |
Apr 11, 2006 | Council Approval Granted |
Apr 11, 2006 | Semi-Monthly Meeting Date Scheduled |
Apr 19, 2006 | Stipulation Package from Biologist |
Apr 19, 2006 | Stipulation Package by Engineer |
Apr 19, 2006 | Typist for Processing |
Apr 19, 2006 | Executive Sign Off |
Apr 19, 2006 | Sent to Photo Copy |
Apr 19, 2006 | Permit Approved |
Apr 24, 2006 | Legal Response/Decision |
Apr 26, 2006 | Under Review/Decision |
Jul 03, 2006 | Land Evidence Date |