Action Date | Action Description |
---|---|
Legal Response/Decision | |
Sep 26, 2005 | Assent Application Received |
Sep 27, 2005 | Administrative Review for Completeness |
Oct 11, 2005 | Deficient Application - Owner Notification Sent |
Nov 04, 2005 | Phone Call |
Nov 22, 2005 | Deficiency Response Received |
Nov 30, 2005 | Team Review for Completeness |
Nov 30, 2005 | Application Accepted |
Nov 30, 2005 | Category B assigned |
Dec 05, 2005 | 30 day Public Notice Issued |
Dec 13, 2005 | HPHC Historical Preservation No Effect |
Jan 05, 2006 | Public Notice End Date |
Jan 10, 2006 | Engineering Report |
Jan 12, 2006 | Biologist Review not required |
Jan 12, 2006 | Supervisor Engineer SignOff |
Jan 12, 2006 | Executive Sign Off |
Feb 06, 2006 | US Army Corp of Engineers Permit Date |
Feb 07, 2006 | Ready to Schedule Semi-Monthly Meeting |
Feb 07, 2006 | Mail Agenda Notice |
Feb 08, 2006 | US Army Corps of Engineers Approval Received |
Feb 14, 2006 | Semi-Monthly Meeting Unexcused Absence |
Feb 14, 2006 | Semi-Monthly Meeting Date Scheduled |
Feb 16, 2006 | Mail Agenda Notice |
Feb 28, 2006 | Semi-Monthly Meeting Held |
Feb 28, 2006 | Council Approval Granted |
Feb 28, 2006 | Semi-Monthly Meeting Date Scheduled |
Apr 25, 2006 | Stipulation Package from Biologist |
Apr 25, 2006 | Stipulation Package by Engineer |
Apr 26, 2006 | Typist for Processing |
Apr 26, 2006 | Executive Sign Off |
Apr 26, 2006 | Sent to Photo Copy |
Apr 26, 2006 | Permit Approved |
May 17, 2006 | Land Evidence Date |