Action Date | Action Description |
---|---|
Nov 25, 2005 | Assent Application Received |
Nov 28, 2005 | Administrative Review for Completeness |
Dec 02, 2005 | Team Review for Completeness |
Dec 02, 2005 | Application Accepted |
Dec 02, 2005 | Category A* (Docks) |
Dec 13, 2005 | HPHC Historical Preservation No Effect |
Dec 14, 2005 | 30 day Public Notice Issued |
Feb 16, 2006 | Correspondence Received |
Feb 17, 2006 | US Army Corp of Engineers Permit Date |
Feb 17, 2006 | US Army Corps of Engineers Approval Received |
Feb 20, 2006 | Public Notice End Date |
Mar 28, 2006 | Biologist Report |
Mar 28, 2006 | Engineering Report |
Mar 31, 2006 | Dock Meeting Scheduled (Admin) |
Mar 31, 2006 | Dock sub-committee Approved |
Apr 03, 2006 | Typist for Processing |
Apr 03, 2006 | Executive Sign Off |
Apr 03, 2006 | Sent to Photo Copy |
Apr 03, 2006 | Permit Approved |
Apr 10, 2006 | Land Evidence Date |