Action Date | Action Description |
---|---|
Dec 06, 2005 | Assent Application Received |
Dec 07, 2005 | Administrative Review for Completeness |
Dec 09, 2005 | Team Review for Completeness |
Dec 09, 2005 | Application Accepted |
Dec 09, 2005 | Category B assigned |
Dec 27, 2005 | 30 day Public Notice Issued |
Jan 01, 2006 | HPHC Historical Preservation No Effect |
Feb 16, 2006 | Correspondence Received |
Feb 17, 2006 | US Army Corp of Engineers Permit Date |
Feb 17, 2006 | US Army Corps of Engineers Approval Received |
Feb 20, 2006 | Public Notice End Date |
Apr 24, 2006 | Biologist Report |
Apr 24, 2006 | Engineering Report |
May 08, 2006 | Supervisor Biologist SignOff |
May 08, 2006 | Supervisor Engineer SignOff |
May 09, 2006 | Executive Sign Off |
May 11, 2006 | Ready to Schedule Semi-Monthly Meeting |
May 11, 2006 | Mail Agenda Notice |
May 23, 2006 | Semi-Monthly Meeting Held |
May 23, 2006 | Council Approval Granted |
May 23, 2006 | Semi-Monthly Meeting Date Scheduled |
Jun 01, 2006 | Stipulation Package from Biologist |
Jun 01, 2006 | Stipulation Package by Engineer |
Jun 01, 2006 | Typist for Processing |
Jun 01, 2006 | Executive Sign Off |
Jun 01, 2006 | Sent to Photo Copy |
Jun 01, 2006 | Permit Approved |
Jun 12, 2006 | Legal Response/Decision |
Jun 26, 2006 | Land Evidence Date |