Action Date | Action Description |
---|---|
Dec 09, 2005 | Assent Application Received |
Jan 10, 2006 | Administrative Review for Completeness |
Feb 01, 2006 | Team Review for Completeness |
Feb 01, 2006 | Application Accepted |
Feb 02, 2006 | Category B assigned |
Feb 08, 2006 | 30 day Public Notice Issued |
Feb 15, 2006 | HPHC Historical Preservation No Effect |
Feb 17, 2006 | Correspondence Received |
Mar 15, 2006 | Correspondence Received |
Mar 16, 2006 | Engineering Report |
Mar 17, 2006 | Public Notice End Date |
Mar 20, 2006 | US Army Corp of Engineers Permit Date |
Mar 22, 2006 | US Army Corps of Engineers Approval Received |
Apr 11, 2006 | Biologist Report |
Jun 05, 2006 | Supervisor Biologist SignOff |
Jun 05, 2006 | Supervisor Engineer SignOff |
Jun 06, 2006 | Executive Sign Off |
Jul 14, 2006 | Ready to Schedule Semi-Monthly Meeting |
Jul 14, 2006 | Mail Agenda Notice |
Jul 25, 2006 | Semi-Monthly Meeting Postponed |
Jul 25, 2006 | Semi-Monthly Meeting Date Scheduled |
Jul 31, 2006 | Ready to Schedule Semi-Monthly Meeting |
Jul 31, 2006 | Mail Agenda Notice |
Aug 08, 2006 | Semi-Monthly Meeting Held |
Aug 08, 2006 | Council Approval Granted |
Aug 08, 2006 | Semi-Monthly Meeting Date Scheduled |
Aug 11, 2006 | Stipulation Package by Engineer |
Aug 16, 2006 | Stipulation Package from Biologist |
Aug 16, 2006 | Typist for Processing |
Aug 16, 2006 | Executive Sign Off |
Aug 16, 2006 | Sent to Photo Copy |
Aug 18, 2006 | Permit Approved |
Aug 21, 2006 | Land Evidence Date |
Sep 15, 2006 | Legal Response/Decision |