Action Date | Action Description |
---|---|
Dec 27, 2005 | Assent Application Received |
Dec 28, 2005 | Administrative Review for Completeness |
Dec 29, 2005 | Team Review for Completeness |
Dec 29, 2005 | Application Accepted |
Jan 04, 2006 | Engineering Report |
Jan 04, 2006 | Typist for Processing |
Jan 04, 2006 | Executive Sign Off |
Jan 04, 2006 | Sent to Photo Copy |
Jan 04, 2006 | Permit Approved |
Jan 10, 2006 | HPHC Historical Preservation No Effect |
Apr 20, 2006 | Land Evidence Date |
Oct 02, 2006 | Correspondence Received |
Oct 02, 2006 | Correspondence Received |
Oct 02, 2006 | Assent Correction Mailed |
Oct 18, 2006 | Land Evidence Date |
Oct 09, 2007 | Modification Request |
Oct 10, 2007 | Administrative Review for Completeness |
Jan 03, 2008 | Team Review for Completeness |
Jan 30, 2008 | HPHC Historical Preservation No Effect |
Feb 05, 2008 | Biologist Report |
Feb 05, 2008 | Typist for Processing |
Feb 05, 2008 | Executive Sign Off |
Feb 05, 2008 | Sent to Photo Copy |
Feb 05, 2008 | Modification Approved |
Feb 20, 2008 | Land Evidence Date |
Apr 14, 2008 | Modification Amended |
Apr 14, 2008 | Modification Correction mailed |
Apr 24, 2008 | Land Evidence Date |