Action Date | Action Description |
---|---|
Jan 13, 2006 | Maintenance Certification Request |
Jan 16, 2006 | Administrative Review for Completeness |
Jan 18, 2006 | Correspondence Mailed/Faxed/E-mailed |
Feb 07, 2006 | Application Accepted |
Feb 07, 2006 | Team Review for Completeness |
Feb 13, 2006 | Biologist Report |
Feb 15, 2006 | HPHC Historical Preservation No Effect |
Feb 17, 2006 | Engineering Report |
Feb 20, 2006 | Typist for Processing |
Feb 20, 2006 | Executive Sign Off |
Feb 20, 2006 | Sent to Photo Copy |
Feb 20, 2006 | Permit Approved |
Mar 20, 2006 | Land Evidence Date |
Jun 19, 2006 | Commencement of Work Notice received |