Action Date | Action Description |
---|---|
Feb 21, 2006 | Assent Application Received |
Feb 23, 2006 | Administrative Review for Completeness |
Apr 07, 2006 | Team Review for Completeness |
Apr 07, 2006 | Application Accepted |
Apr 07, 2006 | Category A* (Docks) |
Apr 19, 2006 | 30 day Public Notice Issued |
Apr 28, 2006 | HPHC Historical Preservation No Effect |
May 01, 2006 | HPHC Historical Preservation No Effect |
May 19, 2006 | Public Notice End Date |
May 30, 2006 | Engineering Report |
Jun 12, 2006 | US Army Corp of Engineers Permit Date |
Jun 16, 2006 | US Army Corps of Engineers Approval Received |
Feb 09, 2007 | Supervisor Engineer SignOff |
Feb 14, 2007 | Executive Sign Off |
Feb 14, 2007 | Supervisor Biologist SignOff |
Feb 14, 2007 | Biologist Report |
Feb 15, 2007 | Ready to Schedule Semi-Monthly Meeting |
Feb 15, 2007 | Mail Agenda Notice |
Feb 27, 2007 | Semi-Monthly Meeting Held |
Feb 27, 2007 | Council Approval Granted |
Feb 27, 2007 | Semi-Monthly Meeting Date Scheduled |
Mar 06, 2007 | Stipulation Package by Engineer |
Mar 07, 2007 | Permit Approved |
Mar 07, 2007 | Typist for Processing |
Mar 07, 2007 | Executive Sign Off |
Mar 07, 2007 | Sent to Photo Copy |
Mar 13, 2007 | Legal Response/Decision |
Mar 13, 2007 | Stipulation Package from Biologist |
Apr 13, 2007 | Land Evidence Date |
Jan 11, 2013 | Additional Information Received |
Jan 14, 2013 | Extension Toll letter mailed |