Action Date | Action Description |
---|---|
Apr 18, 2006 | Assent Application Received |
Apr 18, 2006 | Administrative Review for Completeness |
May 04, 2006 | Team Review for Completeness |
May 04, 2006 | Application Accepted |
May 04, 2006 | Category B assigned |
May 09, 2006 | 30 day Public Notice Issued |
May 17, 2006 | HPHC Historical Preservation No Effect |
Jun 09, 2006 | Public Notice End Date |
Jul 17, 2006 | Biologist Report |
Jul 17, 2006 | Engineering Report |
Jul 20, 2006 | Executive Sign Off |
Aug 11, 2006 | Ready to Schedule Semi-Monthly Meeting |
Aug 11, 2006 | Mail Agenda Notice |
Aug 22, 2006 | Semi-Monthly Meeting Date Scheduled |
Aug 25, 2006 | Mail Agenda Notice |
Aug 25, 2006 | Ready to Schedule Semi-Monthly Meeting |
Sep 12, 2006 | Semi-Monthly Meeting Date Scheduled |
Sep 12, 2006 | Semi-Monthly Meeting Postponed |
Sep 19, 2006 | Ready to Schedule Semi-Monthly Meeting |
Sep 19, 2006 | Semi-Monthly Meeting Held |
Sep 19, 2006 | Council Approval Granted |
Oct 10, 2006 | Stipulation Package from Biologist |
Oct 10, 2006 | Stipulation Package by Engineer |
Oct 10, 2006 | Typist for Processing |
Oct 10, 2006 | Executive Sign Off |
Oct 10, 2006 | Sent to Photo Copy |
Oct 10, 2006 | Permit Approved |
Nov 01, 2006 | Land Evidence Date |
Nov 20, 2006 | Legal Response/Decision |
Sep 27, 2010 | Correspondence Received |