Action Date | Action Description |
---|---|
Aug 07, 2006 | Assent Application Received |
Aug 08, 2006 | Administrative Review for Completeness |
Aug 16, 2006 | Team Review for Completeness |
Aug 16, 2006 | Application Accepted |
Aug 16, 2006 | Category A* (Docks) |
Aug 25, 2006 | HPHC Historical Preservation No Effect |
Aug 30, 2006 | 30 day Public Notice Issued |
Sep 30, 2006 | Public Notice End Date |
Nov 27, 2006 | Additional Information Received |
Jan 24, 2007 | Plans Received |
Feb 14, 2007 | Typist for Processing |
Feb 14, 2007 | Executive Sign Off |
Feb 14, 2007 | Sent to Photo Copy |
Feb 14, 2007 | Permit Approved |
Feb 14, 2007 | Biologist Report |
Feb 14, 2007 | Engineering Report |
Feb 16, 2007 | US Army Corp of Engineers Permit Date |
Feb 20, 2007 | US Army Corps of Engineers Approval Received |
Mar 05, 2007 | Land Evidence Date |
May 29, 2007 | Commencement of Work Notice received |
Mar 26, 2013 | Modification Request |
Mar 26, 2013 | Administrative Review for Completeness |
Mar 27, 2013 | Team Review for Completeness |
Mar 27, 2013 | Team Review for Completeness |
Apr 05, 2013 | HPHC Historical Preservation No Effect |
Apr 23, 2013 | Aquaculture Report |
May 21, 2013 | Engineering Report |
May 22, 2013 | Typist for Processing |
May 22, 2013 | Executive Sign Off |
May 22, 2013 | Sent to Photo Copy |
May 22, 2013 | Modification Approved |