Action Date | Action Description |
---|---|
Aug 09, 2007 | Assent Application Received |
Aug 10, 2007 | Administrative Review for Completeness |
Aug 16, 2007 | Team Review for Completeness |
Aug 16, 2007 | Team Review for Completeness |
Aug 16, 2007 | Application Accepted |
Aug 24, 2007 | HPHC Historical Preservation No Effect |
Jul 09, 2008 | Additional Information Received |
Jul 09, 2008 | Typist for Processing |
Jul 09, 2008 | Executive Sign Off |
Jul 09, 2008 | Sent to Photo Copy |
Jul 09, 2008 | Permit Approved |
Jul 09, 2008 | Biologist Report |
Jul 09, 2008 | Engineering Report |
Jul 22, 2008 | Land Evidence Date |