Action Date | Action Description |
---|---|
Feb 13, 2008 | Assent Application Received |
Feb 14, 2008 | Administrative Review for Completeness |
Feb 20, 2008 | Team Review for Completeness |
Feb 20, 2008 | Team Review for Completeness |
Feb 20, 2008 | Deficient Application - Owner Notification Sent |
Mar 04, 2008 | Deficient Application Picked Up |
Mar 11, 2008 | Deficiency Response Received |
Mar 12, 2008 | Team Review for Completeness |
Mar 12, 2008 | Team Review for Completeness |
Mar 12, 2008 | Application Accepted |
Apr 21, 2008 | HPHC Historical Preservation No Effect |
Feb 24, 2009 | Correspondence Received |
Nov 08, 2010 | Additional Information Received |
Jun 23, 2011 | Additional Information Received |
Jul 07, 2011 | Biologist Report |
Jul 08, 2011 | Typist for Processing |
Jul 08, 2011 | Permit Approved |
Jul 11, 2011 | Executive Sign Off |
Jul 11, 2011 | Sent to Photo Copy |
Nov 22, 2011 | Land Evidence Date |
May 03, 2016 | Extension Toll letter mailed |