Action Date | Action Description |
---|---|
Oct 06, 2011 | Assent Application Received |
Oct 11, 2011 | Administrative Review for Completeness |
Oct 12, 2011 | Team Review for Completeness |
Oct 12, 2011 | Team Review for Completeness |
Oct 12, 2011 | Application Accepted |
Nov 15, 2011 | HPHC Historical Preservation No Effect |
Nov 30, 2011 | Biologist Report |
Dec 02, 2011 | Permit Approved |
Dec 02, 2011 | Typist for Processing |
Dec 02, 2011 | Engineering Report |
Dec 05, 2011 | Executive Sign Off |
Dec 05, 2011 | Sent to Photo Copy |
Jan 04, 2012 | Land Evidence Date |
Apr 09, 2012 | Commencement of Work Notice received |
Jun 17, 2013 | Letter of Authorization |