Action Date | Action Description |
---|---|
Oct 07, 2011 | Assent Application Received |
Oct 10, 2011 | Administrative Review for Completeness |
Oct 11, 2011 | Team Review for Completeness |
Oct 11, 2011 | Team Review for Completeness |
Oct 11, 2011 | Application Accepted |
Nov 22, 2011 | Additional Information Requested from Applicant |
Nov 22, 2011 | 30-Day Notification of Cancellation letter |
Dec 12, 2011 | HPHC Historical Preservation No Effect |
Feb 28, 2012 | Additional Information Received |
Mar 16, 2012 | Additional Information Received |
Mar 26, 2012 | Biologist Report |
Mar 26, 2012 | Engineering Report |
Mar 27, 2012 | Permit Approved |
Mar 27, 2012 | Typist for Processing |
Mar 28, 2012 | Executive Sign Off |
Mar 28, 2012 | Sent to Photo Copy |
Apr 05, 2012 | Land Evidence Date |