Action Date | Action Description |
---|---|
Nov 01, 2011 | Assent Application Received |
Nov 02, 2011 | Administrative Review for Completeness |
Nov 04, 2011 | Team Review for Completeness |
Nov 04, 2011 | Team Review for Completeness |
Nov 04, 2011 | Application Accepted |
Nov 23, 2011 | HPHC Historical Preservation No Effect |
Dec 06, 2011 | 30 day Public Notice Issued |
Jan 06, 2012 | Public Notice End Date |
Apr 04, 2012 | US Army Corps of Engineers Approval Received |
Jun 26, 2012 | Plans Received |
Jun 26, 2012 | Biologist Report |
Jun 26, 2012 | Engineering Report |
Jun 27, 2012 | Permit Approved |
Jun 27, 2012 | Category A* (Docks) |
Jun 27, 2012 | Typist for Processing |
Jun 29, 2012 | Executive Sign Off |
Jun 29, 2012 | Sent to Photo Copy |
Dec 21, 2012 | Land Evidence Date |