Action Date | Action Description |
---|---|
Dec 22, 2011 | Team Review for Completeness |
Dec 22, 2011 | Buffer Zone Management Application Received |
Dec 22, 2011 | Administrative Review for Completeness |
Dec 23, 2011 | Team Review for Completeness |
Dec 23, 2011 | Application Accepted |
Jan 04, 2012 | HPHC Historical Preservation No Effect |
Mar 20, 2012 | 30-Day Notification of Cancellation letter |
Apr 17, 2012 | Correspondence Received |
Apr 18, 2012 | Additional Information Requested from Applicant |
May 22, 2012 | Additional Information Received |
Aug 02, 2012 | 30-Day Notification of Cancellation letter |
Aug 13, 2012 | Certified Receipt Received |
Aug 31, 2012 | Additional Information Received |
Oct 26, 2012 | Additional Information Requested from Applicant |
May 16, 2013 | Additional Information Received |
May 21, 2013 | Additional Information Received |
Jul 08, 2013 | Additional Information Received |
Aug 13, 2013 | Biologist Report |
Aug 13, 2013 | Engineering Report |
Aug 14, 2013 | Permit Approved |
Aug 14, 2013 | Typist for Processing |
Aug 28, 2013 | Executive Sign Off |
Aug 28, 2013 | Sent to Photo Copy |
Sep 12, 2013 | Land Evidence Date |
Oct 21, 2013 | Commencement of Work Notice received |