Action Date | Action Description |
---|---|
Aug 31, 2012 | Assent Application Received |
Aug 31, 2012 | Administrative Review for Completeness |
Sep 04, 2012 | Team Review for Completeness |
Sep 04, 2012 | Team Review for Completeness |
Sep 04, 2012 | Application Accepted |
Sep 27, 2012 | Biologist Report |
Sep 27, 2012 | Engineering Report |
Oct 04, 2012 | Supervisor Biologist SignOff |
Oct 04, 2012 | Supervisor Engineer SignOff |
Oct 09, 2012 | Executive Signoff of Staff Reports |
Oct 16, 2012 | Additional Information Received |
Nov 01, 2012 | HPHC Historical Preservation No Effect |
Nov 26, 2012 | Typist for Processing |
Nov 26, 2012 | Permit Approved |
Nov 27, 2012 | Executive Sign Off |
Nov 27, 2012 | Sent to Photo Copy |
Nov 29, 2012 | Land Evidence Date |
Nov 09, 2018 | Correspondence Mailed/Faxed/E-mailed |