Action Date | Action Description |
---|---|
Nov 05, 2012 | Assent Application Received |
Nov 05, 2012 | Administrative Review for Completeness |
Nov 19, 2012 | Team Review for Completeness |
Nov 19, 2012 | Team Review for Completeness |
Nov 19, 2012 | Application Accepted |
Dec 03, 2012 | HPHC Historical Preservation No Effect |
Jan 18, 2013 | Engineering Report |
Jan 22, 2013 | Permit Approved |
Jan 22, 2013 | Typist for Processing |
Jan 22, 2013 | Executive Sign Off |
Jan 22, 2013 | Biologist Report |
Jan 23, 2013 | Sent to Photo Copy |
Jan 31, 2013 | Land Evidence Date |