Action Date | Action Description |
---|---|
Feb 04, 2013 | Assent Application Received |
Feb 04, 2013 | Administrative Review for Completeness |
Feb 12, 2013 | Team Review for Completeness |
Feb 12, 2013 | Team Review for Completeness |
Feb 12, 2013 | Application Accepted |
Feb 25, 2013 | HPHC Historical Preservation No Effect |
Mar 29, 2013 | Additional Information Requested from Applicant |
Apr 12, 2013 | Additional Information Received |
Apr 24, 2013 | Biologist Report |
Apr 24, 2013 | Engineering Report |
Apr 25, 2013 | Typist for Processing |
Apr 25, 2013 | Permit Approved |
Apr 26, 2013 | Executive Sign Off |
Apr 26, 2013 | Sent to Photo Copy |
May 28, 2013 | Land Evidence Date |