Action Date | Action Description |
---|---|
Mar 11, 2013 | Assent Application Received |
Mar 11, 2013 | Administrative Review for Completeness |
Mar 12, 2013 | Team Review for Completeness |
Mar 12, 2013 | Team Review for Completeness |
Mar 12, 2013 | Application Accepted |
Mar 28, 2013 | Biologist Report |
Mar 28, 2013 | Engineering Report |
Mar 29, 2013 | Typist for Processing |
Mar 29, 2013 | Permit Approved |
Apr 01, 2013 | Executive Sign Off |
Apr 01, 2013 | Sent to Photo Copy |
Apr 03, 2013 | Land Evidence Date |
Apr 05, 2013 | HPHC Historical Preservation No Effect |