Action Date | Action Description |
---|---|
May 21, 2013 | Assent Application Received |
May 22, 2013 | Administrative Review for Completeness |
May 22, 2013 | Team Review for Completeness |
May 22, 2013 | Application Accepted |
Jun 10, 2013 | HPHC Historical Preservation No Effect |
Jun 28, 2013 | Additional Information Requested from Applicant |
Aug 08, 2013 | Additional Information Received |
Aug 14, 2013 | Plans Received |
Oct 01, 2013 | Additional Information Received |
Oct 24, 2013 | Additional Information Received |
Feb 18, 2014 | Additional Information Received |
Apr 02, 2014 | Additional Information Received |
Apr 11, 2014 | Biologist Report |
Apr 21, 2014 | Typist for Processing |
Apr 21, 2014 | Permit Approved |
Apr 22, 2014 | Executive Sign Off |
Apr 22, 2014 | Sent to Photo Copy |
May 09, 2014 | Land Evidence Date |
May 31, 2018 | Expiration of Assent/End of Tolling Legislation |
May 31, 2018 | Modification Request |
Jun 01, 2018 | Administrative Review for Completeness |
Jun 11, 2018 | Team Review for Completeness |
Jun 11, 2018 | Application Accepted |
Jun 26, 2018 | HPHC Historical Preservation No Effect |
Jun 27, 2018 | Comments Received |
Jul 25, 2018 | Additional Information Received |
Aug 15, 2018 | Additional Information Received |
Sep 04, 2018 | Additional Information Received |
Sep 11, 2018 | Additional Information Received |
Oct 12, 2018 | Modification Approved |
Oct 12, 2018 | Biologist Report |
Oct 22, 2018 | Land Evidence Date |
Jun 25, 2019 | Extension of Permit Request |
Sep 11, 2019 | Enforcement Compliance Inspection Required |
Sep 17, 2019 | Process Extension |
Sep 17, 2019 | Extension Approved |