Action Date | Action Description |
---|---|
Aug 16, 2013 | Assent Application Received |
Aug 19, 2013 | Administrative Review for Completeness |
Sep 10, 2013 | Team Review for Completeness |
Sep 10, 2013 | Deficient Application - Owner Notification Sent |
Sep 27, 2013 | Deficient Application Picked Up |
May 22, 2014 | Deficiency Response Received |
May 27, 2014 | Team Review for Completeness |
May 27, 2014 | Application Accepted |
May 29, 2014 | HPHC Historical Preservation No Effect |
Jun 06, 2014 | 30 day Public Notice Issued |
Jul 06, 2014 | Public Notice End Date |
Jul 18, 2014 | Biologist Report |
Jul 21, 2014 | Typist for Processing |
Jul 21, 2014 | Permit Approved |
Jul 22, 2014 | Executive Sign Off |
Jul 22, 2014 | Sent to Photo Copy |
Aug 07, 2014 | US Army Corps of Engineers Approval Received |
Aug 14, 2014 | Land Evidence Date |