Action Date | Action Description |
---|---|
Sep 26, 2013 | Assent Application Received |
Sep 27, 2013 | Administrative Review for Completeness |
Sep 27, 2013 | Team Review for Completeness |
Sep 27, 2013 | Application Accepted |
Oct 04, 2013 | HPHC Historical Preservation No Effect |
Nov 12, 2013 | Geologist Report |
Dec 12, 2013 | Plans Received |
Feb 06, 2014 | 30 day Public Notice Issued |
Mar 05, 2014 | Objections/Comments Received |
Mar 06, 2014 | Public Notice End Date |
Mar 07, 2014 | Objections/Comments Received |
Apr 23, 2014 | Correspondence Received |
Jul 24, 2014 | Additional Information Received |
Feb 20, 2015 | Plans Received |
Oct 12, 2017 | Engineering Report |
Oct 12, 2017 | Biologist Report |
Oct 13, 2017 | Supervisor Engineer SignOff |
Oct 16, 2017 | Supervisor Biologist SignOff |
Oct 17, 2017 | Executive Signoff of Staff Reports |
May 08, 2018 | Ready to Schedule Semi-Monthly Meeting |
May 08, 2018 | Mail Agenda Notice |
May 22, 2018 | Semi-Monthly Meeting Postponed |
May 22, 2018 | Semi-Monthly Meeting Date Scheduled |
Jun 01, 2018 | Objections/Comments Received |
Jun 15, 2018 | Ready to Schedule Semi-Monthly Meeting |
Jun 15, 2018 | Mail Agenda Notice |
Jun 19, 2018 | Correspondence Received |
Jun 26, 2018 | Council Approval Granted |
Jun 26, 2018 | Semi-Monthly Meeting Date Scheduled |
Jul 09, 2018 | Legal Response/Decision |
Aug 20, 2018 | Typist for Processing |
Aug 20, 2018 | Permit Approved |
Aug 20, 2018 | Stipulation Package by Engineer |
Aug 31, 2018 | Land Evidence Date |
Sep 25, 2018 | Assent Correction Mailed |
Mar 04, 2021 | Extension of Permit Request |
May 09, 2022 | Enforcement Compliance Inspection Required |
May 12, 2022 | Process Extension |
May 12, 2022 | Extension Approved |
Jun 16, 2022 | Extension of Permit Request |
May 08, 2023 | Enforcement Compliance Inspection Required |
May 11, 2023 | Process Extension |
May 11, 2023 | Extension Approved |