Action Date | Action Description |
---|---|
Jul 29, 2014 | Team Review for Completeness |
Jul 29, 2014 | Assent Application Received |
Jul 29, 2014 | Administrative Review for Completeness |
Sep 04, 2014 | HPHC Historical Preservation No Effect |
Sep 10, 2014 | Application Accepted |
Sep 10, 2014 | Team Review for Completeness |
Sep 15, 2014 | Biologist Report |
Sep 15, 2014 | Engineering Report |
Oct 02, 2014 | Permit Approved |
Oct 03, 2014 | Typist for Processing |
Oct 03, 2014 | Executive Sign Off |
Oct 03, 2014 | Sent to Photo Copy |