Action Date | Action Description |
---|---|
Aug 20, 2015 | Assent Application Received |
Aug 21, 2015 | Administrative Review for Completeness |
Sep 01, 2015 | Application Accepted |
Sep 02, 2015 | Team Review for Completeness |
Oct 07, 2015 | US Army Corps of Engineers Approval Received |
Oct 19, 2015 | Aquaculture Report |
Oct 19, 2015 | Typist for Processing |
Oct 19, 2015 | Executive Sign Off |
Oct 19, 2015 | Permit Approved |