Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Oct 30, 2017 | Assent Application Received |
Oct 30, 2017 | Administrative Review for Completeness |
Nov 06, 2017 | Team Review for Completeness |
Nov 06, 2017 | Application Accepted |
Nov 06, 2017 | Category A* (Docks) |
Nov 16, 2017 | HPHC Historical Preservation No Effect |
Nov 22, 2017 | 30 day Public Notice Issued |
Dec 22, 2017 | Public Notice End Date |
Dec 22, 2017 | Objections/Comments Received |
Jan 02, 2018 | US Army Corps of Engineers Approval Received |
Feb 02, 2018 | Additional Information Received |
Feb 12, 2018 | Supervisor Biologist SignOff |
Feb 12, 2018 | Supervisor Engineer SignOff |
Feb 12, 2018 | Biologist Report |
Feb 13, 2018 | Executive Signoff of Staff Reports |
Feb 15, 2018 | Ready to Schedule Semi-Monthly Meeting |
Feb 28, 2018 | Mail Agenda Notice |
Mar 05, 2018 | Comments Received |
Apr 10, 2018 | Council Approval Granted |
Apr 10, 2018 | Semi-Monthly Meeting Date Scheduled |
May 10, 2018 | Legal Response/Decision |
May 10, 2018 | 30 Day Appeal Notification to Owner |
May 11, 2018 | Stipulation Package from Biologist |
May 15, 2018 | Typist for Processing |
May 15, 2018 | Executive Sign Off |
May 15, 2018 | Sent to Photo Copy |
May 15, 2018 | Permit Approved |
May 21, 2018 | Land Evidence Date |
Nov 16, 2018 | Modification Request |
Nov 16, 2018 | Administrative Review for Completeness |
Nov 26, 2018 | Team Review for Completeness |
Nov 27, 2018 | Biologist Review not required |
Nov 27, 2018 | Application Accepted |
Dec 07, 2018 | HPHC Historical Preservation No Effect |
Dec 18, 2018 | 30 day Public Notice Issued |
Jan 19, 2019 | Public Notice End Date |
Mar 01, 2019 | Modification Approved |
Mar 01, 2019 | Engineering Report |
Mar 19, 2019 | Land Evidence Date |
Sep 01, 2022 | Dock Plate re-issue |