Action Date | Action Description |
---|---|
Nov 01, 2017 | Assent Application Received |
Nov 02, 2017 | Administrative Review for Completeness |
Nov 15, 2017 | Additional Information Received |
Nov 16, 2017 | Application Accepted |
Dec 05, 2017 | HPHC Historical Preservation No Effect |
Dec 06, 2017 | Engineering Report |
Dec 06, 2017 | Typist for Processing |
Dec 08, 2017 | Executive Sign Off |
Dec 08, 2017 | Sent to Photo Copy |
Feb 08, 2018 | Permit Approved |
Feb 27, 2018 | Land Evidence Date |