Action Date | Action Description |
---|---|
Nov 03, 2017 | Assent Application Received |
Nov 06, 2017 | Administrative Review for Completeness |
Nov 07, 2017 | Team Review for Completeness |
Nov 07, 2017 | Application Accepted |
Nov 08, 2017 | Correspondence Received |
Nov 21, 2017 | HPHC Historical Preservation No Effect |
Nov 22, 2017 | Biologist Report |
Nov 24, 2017 | Typist for Processing |
Nov 24, 2017 | Executive Sign Off |
Nov 24, 2017 | Sent to Photo Copy |
Nov 24, 2017 | Permit Approved |
Nov 30, 2017 | Land Evidence Date |