Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Nov 09, 2017 | Assent Application Received |
Nov 10, 2017 | Administrative Review for Completeness |
Nov 10, 2017 | Team Review for Completeness |
Nov 10, 2017 | Application Accepted |
Nov 10, 2017 | Category A* (Docks) |
Nov 21, 2017 | HPHC Historical Preservation No Effect |
Nov 22, 2017 | Additional Information Requested from Applicant |
Dec 04, 2017 | Additional Information Received |
Dec 05, 2017 | 30 day Public Notice Issued |
Jan 05, 2018 | Public Notice End Date |
Feb 14, 2018 | Dock Meeting Scheduled (Admin) |
Feb 14, 2018 | Meeting Held |
Feb 15, 2018 | Typist for Processing |
Feb 15, 2018 | Executive Sign Off |
Feb 15, 2018 | Sent to Photo Copy |
Feb 15, 2018 | Permit Approved |
Feb 15, 2018 | Biologist Report |
Feb 15, 2018 | Engineering Report |
Mar 05, 2018 | Land Evidence Date |