Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 14, 2017 | Assent Application Received |
Dec 15, 2017 | Administrative Review for Completeness |
Dec 19, 2017 | Team Review for Completeness |
Dec 19, 2017 | Application Accepted |
Dec 19, 2017 | Category A* (Docks) |
Jan 26, 2018 | HPHC Historical Preservation No Effect |
Jan 30, 2018 | 30 day Public Notice Issued |
Mar 01, 2018 | Public Notice End Date |
May 01, 2018 | Dock/1.1.6 Review approval |
May 23, 2018 | Engineering Report |
May 24, 2018 | Typist for Processing |
May 24, 2018 | Executive Sign Off |
May 24, 2018 | Sent to Photo Copy |
May 24, 2018 | Permit Approved |
Jul 12, 2018 | Land Evidence Date |