Action Date | Action Description |
---|---|
Dec 18, 2017 | Assent Application Received |
Dec 18, 2017 | Administrative Review for Completeness |
Jan 08, 2018 | Team Review for Completeness |
Jan 08, 2018 | Deficient Application - Owner Notification Sent |
Feb 12, 2018 | Deficiency Response Received |
Feb 13, 2018 | Additional Information Received |
Mar 06, 2018 | Team Review for Completeness |
Mar 06, 2018 | Application Accepted |
Mar 07, 2018 | Biologist Report |
Mar 07, 2018 | Permit Approved |
Mar 07, 2018 | Typist for Processing |
Mar 07, 2018 | Executive Sign Off |
Mar 07, 2018 | Sent to Photo Copy |
Jul 19, 2018 | Land Evidence Date |