Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 26, 2017 | Assent Application Received |
Dec 26, 2017 | Administrative Review for Completeness |
Dec 28, 2017 | Team Review for Completeness |
Dec 29, 2017 | Application Accepted |
Dec 29, 2017 | Category A* (Docks) |
Jan 26, 2018 | HPHC Historical Preservation No Effect |
Feb 12, 2018 | 30 day Public Notice Issued |
Mar 14, 2018 | Public Notice End Date |
Apr 27, 2018 | Plans Received |
May 01, 2018 | Biologist Report |
May 01, 2018 | Dock/1.1.6 Review approval |
May 02, 2018 | Permit Approved |
May 02, 2018 | Typist for Processing |
May 02, 2018 | Executive Sign Off |
May 02, 2018 | Sent to Photo Copy |
May 18, 2018 | Land Evidence Date |