Action Date | Action Description |
---|---|
Jan 18, 2018 | Assent Application Received |
Jan 19, 2018 | Administrative Review for Completeness |
Jan 19, 2018 | Category A* (Docks) |
Jan 23, 2018 | Application Accepted |
Jan 23, 2018 | Team Review for Completeness |
Jan 30, 2018 | 30 day Public Notice Issued |
Jan 30, 2018 | Additional Information Requested from Applicant |
Jan 31, 2018 | Plans Received |
Feb 01, 2018 | Correspondence Received |
Feb 02, 2018 | HPHC Historical Preservation No Effect |
Mar 01, 2018 | Public Notice End Date |
Apr 06, 2018 | Biologist Report |
Apr 09, 2018 | Engineering Report |
Apr 09, 2018 | Typist for Processing |
Apr 09, 2018 | Executive Sign Off |
Apr 09, 2018 | Sent to Photo Copy |
Apr 09, 2018 | Permit Approved |
Aug 09, 2018 | Land Evidence Date |
Apr 10, 2019 | Modification Request |
Apr 10, 2019 | Administrative Review for Completeness |
Apr 15, 2019 | Team Review for Completeness |
Apr 15, 2019 | Application Accepted |
May 01, 2019 | Plans Received |
May 02, 2019 | Dock Meeting -- Approval |
May 10, 2019 | HPHC Historical Preservation No Effect |
May 10, 2019 | HPHC Review Pending |
May 21, 2019 | Engineering Report |
May 23, 2019 | Typist for Processing |
May 23, 2019 | Executive Sign Off |
May 23, 2019 | Sent to Photo Copy |
May 23, 2019 | Modification Approved |
Jun 24, 2019 | Land Evidence Date |
Feb 18, 2020 | US Army Corps of Engineers Approval Received |
Mar 11, 2021 | Correspondence Mailed/Faxed/E-mailed |
May 21, 2021 | 30-Day Notification of Cancellation letter |
May 21, 2021 | Additional Information Requested from Applicant |
May 28, 2021 | Correspondence Received |
May 28, 2021 | Correspondence Mailed/Faxed/E-mailed |
Jul 26, 2021 | Dock Post-Construction Certification by Engineer received. |
Jul 26, 2021 | Assent Requirement |
Dec 13, 2021 | Note to File |
Jul 28, 2022 | Modification Request |
Aug 03, 2022 | Administrative Review for Completeness |
Aug 17, 2022 | Bio Team Review for Completeness |
Aug 17, 2022 | Project Manager |
Sep 06, 2022 | HPHC Historical Preservation No Effect |
Sep 12, 2022 | 30 day Public Notice Issued |
Oct 03, 2022 | Biologist Report |
Oct 05, 2022 | Engineering Report |
Oct 12, 2022 | Public Notice End Date |
Oct 17, 2022 | Typist for Processing |
Oct 17, 2022 | Executive Sign Off |
Oct 17, 2022 | Sent to Photo Copy |
Oct 17, 2022 | Modification Approved |
Feb 21, 2023 | Land Evidence Date |