Action Date | Action Description |
---|---|
Mar 05, 2018 | Assent Application Received |
Mar 05, 2018 | Administrative Review for Completeness |
Mar 09, 2018 | Team Review for Completeness |
Mar 09, 2018 | Application Accepted |
Mar 20, 2018 | HPHC Historical Preservation No Effect |
May 04, 2018 | Plans Received |
May 09, 2018 | Biologist Report |
May 10, 2018 | Typist for Processing |
May 10, 2018 | Executive Sign Off |
May 10, 2018 | Sent to Photo Copy |
May 10, 2018 | Permit Approved |
May 21, 2018 | Land Evidence Date |