Action Date | Action Description |
---|---|
Mar 19, 2018 | Assent Application Received |
Mar 19, 2018 | Administrative Review for Completeness |
Mar 27, 2018 | Additional Information Received |
Apr 05, 2018 | Plans Received |
Apr 05, 2018 | Application Accepted |
Apr 05, 2018 | Team Review for Completeness |
Apr 20, 2018 | HPHC Historical Preservation No Effect |
May 03, 2018 | Biologist Report |
May 04, 2018 | Typist for Processing |
May 04, 2018 | Executive Sign Off |
May 04, 2018 | Sent to Photo Copy |
May 04, 2018 | Permit Approved |
Jun 07, 2018 | Land Evidence Date |
Apr 23, 2019 | Modification Request |
Apr 23, 2019 | Administrative Review for Completeness |
Apr 23, 2019 | Team Review for Completeness |
Apr 23, 2019 | Application Accepted |
May 10, 2019 | HPHC Historical Preservation No Effect |
May 10, 2019 | HPHC Review Pending |
Jul 09, 2019 | Plans Received |
Jul 10, 2019 | Modification Approved |
Jul 10, 2019 | Biologist Report |
Feb 06, 2020 | Land Evidence Date |