Action Date | Action Description |
---|---|
Feb 19, 2020 | Assent Application Received |
Feb 19, 2020 | Administrative Review for Completeness |
Feb 24, 2020 | Eng Team Review for Completeness |
Feb 24, 2020 | Application Accepted |
Mar 05, 2020 | Engineering Report |
Mar 09, 2020 | HPHC Historical Preservation No Effect |
Mar 09, 2020 | HPHC Review Pending |
Mar 13, 2020 | Typist for Processing |
Mar 13, 2020 | Executive Sign Off |
Mar 13, 2020 | Sent to Photo Copy |
Mar 13, 2020 | Permit Approved |
Apr 15, 2020 | Land Evidence Date |