Action Date | Action Description |
---|---|
CHA -- application modified due to CHA info | |
Permit Mailed | |
Aug 06, 2021 | Assent Application Received |
Aug 11, 2021 | Administrative Review for Completeness |
Aug 11, 2021 | CHA Worksheet received |
Aug 26, 2021 | Eng Team Review for Completeness |
Aug 26, 2021 | Deficient Application - Owner Notification Sent |
Sep 03, 2021 | Deficiency Response Received |
Sep 13, 2021 | Eng Team Review for Completeness |
Sep 13, 2021 | Application Accepted |
Sep 14, 2021 | Project Manager |
Oct 06, 2021 | Engineering Report |
Oct 06, 2021 | Stipulation Package by Engineer |
Oct 07, 2021 | Typist for Processing |
Oct 07, 2021 | Executive Sign Off |
Oct 07, 2021 | Sent to Photo Copy |
Oct 07, 2021 | Permit Approved |
Oct 13, 2021 | HPHC Review Pending |
Oct 13, 2021 | HPHC Historical Preservation No Effect |
Jan 11, 2022 | Land Evidence Date |