Action Date | Action Description |
---|---|
Aug 10, 2021 | Assent Application Received |
Aug 11, 2021 | Administrative Review for Completeness |
Aug 12, 2021 | Additional Information Requested from Applicant |
Aug 13, 2021 | CHA Worksheet received |
Aug 25, 2021 | Application Accepted |
Aug 25, 2021 | Project Manager |
Aug 25, 2021 | Bio Team Review for Completeness |
Sep 16, 2021 | HPHC Review Pending |
Sep 16, 2021 | HPHC Historical Preservation No Effect |
Sep 27, 2021 | Additional Information Requested from Applicant |
Sep 29, 2021 | Plans Received |
Oct 20, 2021 | Biologist Report |
Oct 21, 2021 | Typist for Processing |
Oct 21, 2021 | Permit Approved |
Oct 25, 2021 | Permit Mailed |
Jan 12, 2022 | Land Evidence Date |