Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Jan 31, 2022 | Assent Application Received |
Feb 01, 2022 | Administrative Review for Completeness |
Feb 01, 2022 | Bio Team Review for Completeness |
Feb 01, 2022 | Application Accepted |
Feb 02, 2022 | Category A* (Docks) |
Feb 03, 2022 | Project Manager |
Feb 11, 2022 | HPHC Review Pending |
Feb 11, 2022 | HPHC Historical Preservation No Effect |
Feb 22, 2022 | 30 day Public Notice Issued |
Mar 21, 2022 | Objections/Comments Received |
Mar 22, 2022 | Public Notice End Date |
Mar 25, 2022 | Objection withdrawal received |
May 06, 2022 | Dock Meeting -- Approval |
May 10, 2022 | Biologist Report |
May 13, 2022 | Typist for Processing |
May 13, 2022 | Permit Approved |
May 16, 2022 | Permit Mailed |
May 16, 2022 | Executive Sign Off |
May 16, 2022 | Sent to Photo Copy |
May 25, 2022 | Land Evidence Date |