Application 2022-11-029 Details

Back to List


Actions:

Action Date Action Description
Nov 09, 2022 CHA Worksheet received
Nov 09, 2022 Assent Application Received
Nov 15, 2022 Administrative Review for Completeness
Nov 18, 2022 Bio Team Review for Completeness
Nov 18, 2022 Application Accepted
Nov 21, 2022 Project Manager
Nov 22, 2022 HPHC Historical Preservation No Effect
Feb 10, 2023 Biologist Report
Feb 21, 2023 Typist for Processing
Feb 21, 2023 Executive Sign Off
Feb 21, 2023 Sent to Photo Copy
Feb 21, 2023 Finding Of No Significant Impact (FONSI)
Feb 23, 2023 Note to File
Feb 24, 2023 Permit Mailed

Details:

File No
2022-11-029
Town
Charlestown
First Name
CRI Managed Solutions
Last Name
Street
Lou Avenue
Location
69 Lou Avenue
Plat/Map
3
Lot/Block
71
Decision Date
Dock Reg.No
Project
As-built pole foundation & flagpole
Description
Water Area
Easement
0
Acceptance Date
Feb 21, 2023

Back to List