Action Date | Action Description |
---|---|
Nov 10, 2022 | Maintenance Certification Request |
Nov 16, 2022 | Administrative Review for Completeness |
Nov 30, 2022 | Eng Team Review for Completeness |
Nov 30, 2022 | Deficient Application - Owner Notification Sent |
Dec 28, 2022 | Deficient Application Picked Up |
Feb 20, 2023 | Deficiency Response Received |
Mar 07, 2023 | Eng Team Review for Completeness |
Mar 07, 2023 | Deficient Application - Owner Notification Sent |
Mar 24, 2023 | Deficiency Response Received |
Mar 27, 2023 | Eng Team Review for Completeness |
Mar 27, 2023 | Application Accepted |
Mar 27, 2023 | Permit Approved |
Mar 28, 2023 | Permit Mailed |