Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 12, 2022 | Assent Application Received |
Dec 16, 2022 | Administrative Review for Completeness |
Dec 16, 2022 | Bio Team Review for Completeness |
Dec 16, 2022 | Application Accepted |
Dec 16, 2022 | Project Manager |
Dec 16, 2022 | Category A* (Docks) |
Jan 10, 2023 | HPHC Historical Preservation No Effect |
Mar 13, 2023 | Additional Information Received |
Mar 29, 2023 | 30 day Public Notice Issued |
Apr 27, 2023 | Objections/Comments Received |
Apr 28, 2023 | Public Notice End Date |
May 03, 2023 | Objections/Comments Received |
May 25, 2023 | Objections/Comments Received |
May 28, 2023 | Public Notice End Date Extension Granted |
May 30, 2023 | Objections/Comments Received |
Jun 14, 2023 | Mail Agenda Notice |
Jun 19, 2023 | Biologist Report |
Jun 21, 2023 | Supervisor Biologist SignOff |
Jun 22, 2023 | Supervisor Engineer SignOff |
Jun 22, 2023 | Executive Signoff of Staff Reports |
Jun 27, 2023 | Council Approval Granted |
Jun 27, 2023 | Semi-Monthly Meeting Date Scheduled |
Jul 03, 2023 | Additional Information Received |
Jul 20, 2023 | Plans Received |
Oct 04, 2023 | Legal Response/Decision |
Nov 08, 2023 | Stipulation Package from Biologist |
Nov 09, 2023 | Typist for Processing |
Nov 09, 2023 | Executive Sign Off |
Nov 09, 2023 | Sent to Photo Copy |
Nov 09, 2023 | Permit Approved |
Nov 14, 2023 | Permit Mailed |
Dec 05, 2023 | Land Evidence Date |
Aug 27, 2024 | Commencement of Work Notice received |