Action Date | Action Description |
---|---|
Dec 21, 2022 | Assent Application Received |
Dec 23, 2022 | Administrative Review for Completeness |
Dec 23, 2022 | Bio Team Review for Completeness |
Dec 23, 2022 | Application Accepted |
Dec 23, 2022 | Project Manager |
Jan 10, 2023 | HPHC Historical Preservation No Effect |
Feb 09, 2023 | 30-Day Notification of Cancellation letter |
Mar 29, 2023 | Plans Received |
Apr 07, 2023 | Biologist Report |
May 09, 2023 | Typist for Processing |
May 09, 2023 | Executive Sign Off |
May 09, 2023 | Sent to Photo Copy |
May 09, 2023 | Permit Approved |
May 11, 2023 | Permit Mailed |
May 22, 2023 | Land Evidence Date |